Earth Notes: On A Wind, Solar EU-US Transatlantic Interconnector (2017)
Updated 2024-12-20.
10%+ of European peak generation capacity interconnect with the US? Smooth demand, share PV, and catch Atlantic weather fronts! #INTUS #superGrid
As of 2015 the EU was driving members to cover ~10% of peak electricity demand with interconnection capacity. The motivation is to help reduce fuel and reserve costs and improve reliability. Also to provide better geographic diversity of intermittent renewables such as wind and sun. This supergrid should extend beyond the EU itself and wider Europe, to the south, the east, and over the Atlantic to the west.
The EU is small enough geographically that on the east-west axis it does not much (for solar PV) spread out sunrise/sunset and time-driven demand peaks. Nor does it always escape from under one weather system for wind. This increases demand for storage and demand-callable thermal plant, eg biomass or Energy from Waste (EfW), or, in the short-term, fossil gas.
One avenue for improvement is to link eastwards to Russia's 8-timezone E-W span IPS/UPS. Especially if it were to also string lots of PV and wind along a much-reinforced grid. Politically and technically that does not seem likely right now. Interconnecting IPS/UPS and ENTSO-E would span 13 timezones.
Running south, closer to or even across the equator to reduce seasonal effects, would be good too. But DESERTEC and similar on a large scale seem unlikely for primarily political/stability reasons for the near future.
(Around-noon US east coast peak solar generation could join the flow to feed Europe's peak evening demand.)
Ambitiously, floating transatlantic windfarms could be strung out along the interconnector to inject power from weather systems across the Atlantic itself (and the jetstream), for further firming of supply...
These sorts of distances are being covered by HVDC projects in China (2090km) and Brazil. With potential losses around 15% or less (~3.5% per 1000km) may be better than storage efficiency (typical 20--25% round-trip losses for pumped hydro) in terms of grid balancing. (Cf 2019 Chinese 3300km 12GW 10%-loss link.)
Starting from the 2002 EU goal of each country to have ~10% of capacity as interconnection, 10% of US/EU generation would imply something like 70--100GW of interconnection, which is basically bigger than the grid capacity of any of the countries on the European western seaboard, so would likely have to be spread out over them, eg Ireland, GB, Spain, Portugal, France, possibly even some via Iceland. Any build would presumably be incremental, in tandem with intra-US and intra-EU transmission reinforcement and renewables build-out to support the Atlantic flows.
Why INTUS? ELEXON refers to the various interconnectors to the GB grid, in (for example) the FUELINST dataset, with the prefix INT.
2017-08-24: Brexit
It is not clear if Brexit would make INTUS significantly harder to achieve. If the UK somehow remains in the European Energy Union then possibly not.